Gleniffer Road Upgrade

3D design of Gleniffer Road Upgrade.

Design Complete: September 2022

Gleniffer Road Upgrade site post construction.

Construction Complete: October 2023

Project Summary

CWC delivered the pre-construction services for the upgrade of Gleniffer Road in collaboration with Bellingen Shire Council.

The Project involved the detailed design of 6km’s of high speed rural road in a highly constrained environment.

Project challenges involved working through trade-offs between road user safety, environment and project costs.

Delivered by Collins Williams

  • Survey and Drone Imagery

  • Geotechnical Investigations

  • Options Assessment

  • Concept Design

  • Detail Design

  • Environmental Approval (REF)

  • Cost Estimation

  • Tender and Contract Documentation

Design Value:

Construction Value:

$200k

$5.3M

Design Lead
Hayden Williams

Project Manager
Michael Collins

A stylized map of the Bellingen area surrounding the Gleniffer Road upgrade, with the site highlighted in dark green.
Previous
Previous

Lorne Road Upgrade & Sealing

Next
Next

Old Bar Road Upgrade